Major Pipeline Interruption and Support Project
Behind the scenes in the MidAtlantic Region
UCNG was contracted to hold a major market, which included the Greenbrier Complex, during a pipeline outage required for an extended pigging project. This involved gas injection at six separate locations, LNG, CNG and a Virtual CNG Pipeline from a seventh site.
MAJOR PIPELINE INTERRUPTION SUPPORT PROJECT
JULY 2023
MID-ATLANTIC REGION, USA
Duration
- 14 days
Six Injection Points
- LNG, CNG & a Virtual CNG Pipeline required.
Equipment and Personnel Utilized:
- A project management team capable of delivering real-time data 24/7 on gas consumption, anticipated demand, and LNG and CNG tanker movements and delivery LNG equipment, CNG equipment, Compressors, Trucks & Drivers, LNG & CNG Operators and Project Managers
Scope:
- Holding the customer’s market by means of six separate injection points for the duration of the pipeline interruption project. Through a combination of LNG, CNG, and our compressors for a virtual pipeline from a connection on the customer’s live pipeline at a separate location.
Impact
- Contracted to supply over 2,000 MCFD at six separate injection points
- Providing a virtual CNG pipeline capable of delivering over 2,400 MCFD